PROJECT MILESTONES 
(02-22-13)


PAST
  Idea Conceived January 2008
  Feasibility Study August 2008
  Wind Monitoring June 2008 - August 2009
  Private Grants Sought Fall 2008
  Power Company Agreements, Prelim. July 2009
  Federal Grants Obtained November 2009 - May 2010
  City Approval Obtained May 2010
  Final FAA Approval Obtained August 2010
  Environmental Assessment June 2010 - February 2011
  Contracts Awarded April 2011
  Foundation & Electrical November 2011
  Turbine & Tower Delivered December 2011
  Installation Dec. 2011 - Feb. 2012
  Commissioning March 2012
  On the Grid April 2012